Futuristic metal stamping plant. Machine installation

Carron Concrete Services was engaged by Dana to Design and Construct a fully integrated Building for this futuristic metal stamping plant. The new building is 1200 square meters in area, 15 meters in height, and a foundation pit  6 meters in depth. The building structure has crane rails for a twin 25 tonne crane of 30 meter bridge span. The site provided challenges  for below ground construction as it is in saturated sand with ground water at 900-mm. Carron Concrete services completed the project on time and on Budget.

Scrap conveyor,and installation of press.

Dana-installation1

Dana-installation2 Dana-installation3 Dana-installation4

Futuristic metal stamping plant. Building construction

Carron Concrete Services was engaged by Dana to Design and Construct a fully integrated Building for this futuristic metal stamping plant. The new building is 1200 square meters in area, 15 meters in height, and a foundation pit  6 meters in depth. The building structure has crane rails for a twin 25 tonne crane of 30 meter bridge span. The site provided challenges  for below ground construction as it is in saturated sand with ground water at 900-mm. Carron Concrete services completed the project on time and on Budget.

Structural steel,site cast Tilt up panels 30 tonnes each,

Dana-Building-construction1

Dana-Building-construction2 Dana-Building-construction3 Dana-Building-construction4

Futuristic metal stamping plant. Construction

Carron Concrete Services was engaged by Dana to Design and Construct a fully integrated Building for this futuristic metal stamping plant. The new building is 1200 square meters in area, 15 meters in height, and a foundation pit  6 meters in depth. The building structure has crane rails for a twin 25 tonne crane of 30 meter bridge span. The site provided challenges  for below ground construction as it is in saturated sand with ground water at 900-mm. Carron Concrete services completed the project on time and on Budget.

The following are phots of the construction of the press pit.

Dana-construction1

Dana-construction2 Dana-construction5 Dana-construction6

Futuristic metal stamping plant. Excavation

Carron Concrete Services was engaged by Dana to Design and Construct a fully integrated Building for this futuristic metal stamping plant. The new building is 1200 square meters in area, 15 meters in height, and a foundation pit  6 meters in depth. The building structure has crane rails for a twin 25 tonne crane of 30 meter bridge span. The site provided challenges  for below ground construction as it is in saturated sand with ground water at 900-mm. Carron Concrete services completed the project on time and on Budget.

Following photos show Demolition and installation of secant pile for 6meter deep foundation pit.

Dana-demolition2

Dana-demolition1 Dana-demolition3 Dana-demolition5

Tight squeeze for 100 tonne crane to leave site after erecting on site tilt up panels for 2 level office building in Richmond.

A good operator, hydralic suspension and crab steering makes it possible.

Crane-very-close-fit

Crane-on-site Crane-close-fit Just-the-cab-to-go

Job-well-done-Crane-out

Under  pinning to neighbours complete. blinding concrete poured, preparing base slab.

Slab-base

Panels-delivered 5-Tonne-panels Panels-installed

Panels-alignment Perimiter-drain Perimiter-drain2

Construction of 6 meter deep pit in unstable saturated sand with water table at 1.2 meters below ground level. No worries, we have the solutions as these photos show.

Building an upside down pit. Construct the top 3 meters before you excavate the bottom 3 meters.

Excavation-below-3M

Excavation-at-10M Excavation-detail Slab-preparations

No-water-in-the-pit

No sign of water in pit, the de-watering working fine. After base is poured and cured, the pumps are turned off and the pit was water tight.

Sheet metal slitting & cropping  line machine foundation for Toyota.

9M-deep-excavation

Preparing-reo-cages Concrete-panels checking-the-props

Lowering-more-panels Near-final-position Pit-showing-machine-pedatals

1-hectare-building-complete

Excavation completed & pouring of 600 mm blinding concrete layer with super plasticiser.

Pouring-with-super-plasticser

Pouring-of-binding-concrete Pouring-of-binding-layer Finishing-machine-base-slab

Finishing-machine-base-slab2 Machine-base-ready Bolt-hole-pockets-and-coolant-sumps